Eustream announces the Open Season procedure SK-UA

Eustream announces Open Season procedure for the increased interruptible capacity at Budince interconnection point, in order to transparently offer such capacity. Eustream provides additional pipeline capacity of 8.5 million cubic meters per day (88,400 MWh) in response to the technical measures taken at the Ukrainian side, which have resulted in increase of pipeline capacity.

19.12.2014

Eustream was informed by MGT about technical problems, which prevent the test operation of SK-HU gas pipeline

In recent days, Hungarian company Magyar Gáz Tranzit Zrt. (MGT) has repeatedly informed Eustream about the technical problems at Szada compressor station, which cause delay of the test operation of Slovak-Hungarian pipeline.

15.12.2014

Notification about Open Season Procedure of the SK-HU Interconnector

- Due to circumstances beyond the control of the TSOs the currently published Rules of the Open Season for the SK-HU Interconnector will be significantly modified, - Therefore the organizing TSOs decided to withdraw the currently published SK-HU Interconnector Open Season Rules, - The expected new Rules of the Open Seasons will be available and published by the 17th of December 2014, - The organizing TSOs ask Applicants not to send binding bids and submissions until further notice

12.12.2014

Change in the deadline for submission of the binding bids in Open Season for the SK-HU Interconnector

The deadline for submission of the binding bids in Open Season for the SK-HU Interconnector is prolonged to Wednesday the 17th December 2014 at 16:00 CET. The organizing TSOs are at this moment also considering the modification of time period of the offered capacities in the actual Open Season Rules.

24.11.2014

Eustream is prepared to put the Slovak-Hungarian pipeline into operation

Eustream is prepared to put the Slovak-Hungarian pipeline into test operation. Company filled the pipeline with gas and prepared the transmission system for the flow test. All systems have been checked and adjusted in order to enable immediate start of the transmission.